No. Only time items associated with incomplete projects and tasks are copied over. Furthermore, if the target week already contains a time item associated with the same project or task and with the same time type, the time item in the target week will not be altered nor will another time item be added in […]
Category: Time
Anything time related (timesheets, the Time Clock system, time approval, time reports, etc.).
How do I approve only one user’s time sheets?
To approve a user’s time sheets more efficiently, you can filter all weeks to display only those of this specific user. To do so, go to “Time Approval” (“Week View” or “Item View”) and select a user from the “All Users” drop-down located in the Filters section.
How can I delete a time item?
The sequence of steps you have to go through to delete one of your time items is the following: Select Home => Time > My Time. Use the navigation tools to reach the weekly timesheet in which the time item you want to delete is located. Select the time item you want to delete. In […]
How are Actual Hours calculated?
Actual Hours are calculated based on timesheet entries recorded by users. For information on the different ways for users to record actual hours in AceProject, please refer to the following help topic.
When copying time items from one week to another, are all selected items copied?
No. Only time items associated with incomplete projects and tasks are copied over. Furthermore, if the target week already contains a time item associated with the same project or task and with the same time type, the time item in the target week will not be altered nor will another time item be added in […]
How are statistics affected by rejected timesheets?
Rejected time is not included in the actual hours computation. On the other hand, time recorded in time items under any other status ( “In Progress”, “Submitted” or “Approved” ) is taken into consideration in the actual hours computation.