When the “Allocation based on %Done and actual hours” mode is selected, AceProject uses the %Done value on a task and the user’s actual hours on that task to compute the number of remaining hours the user has on the task. The system then divides these hours evenly among the number of working days left to complete the task (up to and including its Estimated End Date).
Finally, AceProject adds up the hours assigned to the user for each day. The task %Done values must therefore be updated regularly for the user workload report to present accurate numbers in the “Allocation based on %Done and actual hours” mode.